Skip navigation

Edgewood Park

Sunnyside Saddle Club Park

Edgewood Park is now under construction and closed to the public. Following a hazard tree assessment and arboricultural review, 20 trees were identified to pose a significant public safety concern or will be negatively impacted by necessary grading while constructing the park. 93 new trees are planned to be planted in the park. Construction of some areas of the park will be completed and open to public in late 2020.

Location

2284 165 St, Surrey BC

About Edgewood Park

Acquired in 1951, this 3.9 hectare (9.6 acres) park served as the location for the Sunnyside Saddle Club for many decades. It is now in the middle of a rapidly growing neighbourhood and will be transformed into the next great neighbourhood park.

The park was designed through a community consultation process including two open houses (November 28, 2017 and May 8, 2018) and a community site meeting on February 3, 2020.

After preliminary project work, collecting feedback from residents, revising the concept plan and finalizing detail design plans, the park is now under construction. Some areas of the park are scheduled to open in late 2020.

Project Timeline

    Collapse/Expand All
  • Project Development expand
  • 2017

    This phase involved project scoping, schedule development, and project budgeting.

  • Site Analysis expand
  • Fall 2017 – Spring 2020

    This phase involved site surveying, environmental assessments, other analysis, preliminary design work and site preparation.

  • Community Engagement expand
  • Nov 2017 – Feb 2020

    This phase included: public Open House #1 (Nov 28 2017), public Open House #2 (May 8, 2018), a Community Site Meeting (Feb 3, 2020), feedback and surveys on preliminary design work for the Park.

  • Detailed Design expand
  • Fall 2019 – Summer 2020

    This phase involves the refinement of the park concept design, detailed design, permitting and approvals.

  • Construction expand
  • Starting May 2020

    Construction of Edgewood Park began in May 2020. Some areas of the park are scheduled to open in late 2020.

More Information

For more information contact Mary Wong at mary.wong@surrey.ca.